|
 
[Preface]
[Overview] [History] [Buyout or Bailout?] [Garden City & Beyond]
[Conclusion] [References] [Appendix]
1984 Flood
The flood of Memorial Day '84 made Tulsa's previous record flood of Memorial Day '76 look
like a practice drill. This time, up to 15 inches of rain fell in no more than six hours,
again centered on the Mingo Creek basin but extending throughout much of the city. The
results were devastating.
The
1984 flood killed 14, injured 288, and left $180 million in damages citywide. Mingo Creek
alone accounted for $125 million of the damages.
In the chaotic hours during the flood, a small team of city managers gathered in the
basement Emergency Operations Center. Information was sparse and conflicting; they could
hardly believe the fragmented reports they were receiving. The team was headed by Mayor
Terry Young and Street Commissioner J.D. Metcalfe. Both had come into office only 19 days
before, but both had been involved with Tulsa's drainage issues for years. In the darkest
hours of the flood, the team vowed to try a different kind of flood recovery this time.
Thus was born Tulsa's largest floodplain clearance and mitigation program. By daylight,
Young and Metcalfe were convening experts to develop a recovery and mitigation program. They
hired three consultants to develop the plan. In the lead was Charles Hardt, the former
city chief hydrologist, by 1984 a consultant with McLaughlin Water Engineers, working on
flood control in Tulsa and around the nation. The other two consultants were Stan
Williams, the former city planner, now an attorney who had recently completed a stint with
FEMA where he led the staff group that developed a landmark process for dispatching
federal interagency hazard-mitigation teams following disasters; and Ron Flanagan, a Tulsa
planning consultant who had been working on Tulsa flood issues since the early 1970s.
The
city set up its own in-house Tulsa Flood-Hazard Mitigation Team, and the McLaughlin team
set to work before their contract was drafted. They spearheaded a survey of flooded areas,
with the Corps of Engineers, city engineers, and a flock of volunteers from the private
engineering community.
Within 72 hours after the flood, they had prepared maps showing the extent of flooding,
including identification of the most critical areas. In less than two weeks after the
flood, they had identified target buy-out areas, and Tulsa's 1984 flood-hazard mitigation
program was well under way.
1984 program
They proceeded with a great sense of urgency.
The leadership team knew that a federal interagency hazard-mitigation team would be coming
to Tulsa shortly, to issue mitigation recommendations within 15 days after the May 31
disaster declaration. Tulsa leaders determined to meet them coming in with local
recommendations, couched so persuasively that the feds would agree.
The Tulsa team wanted to help victims stabilize their lives as quickly as possible, while
still seizing the opportunities for change that would exist only briefly after the flood.
In Tulsa, frequently flooded victims had considerable experience with rebuilding; victims
and the government historically made the most critical decisions within the first three
days after a flood. The victims, as a group, seemed to move rapidly through several trauma
stages: shock, euphoria at still being alive, determination to rebuild their lives, and
tremendous grief and anger. According to Tulsa's past pattern, within three days the City
Commission would convene in emergency session, waive building permits and fees for
victims, and set about trying to help them rebuild.
After the 1984 flood, the city team deliberately tried to slow that process down, until it
could determine whether it might be possible to clear some of the flooded houses before they
were rebuilt, leveraging local funds with flood insurance and other post-disaster funds.
The staff knew that "substantially damaged" buildings could not be rebuilt
unless they complied with federal flood regulations --- and the city intended to comply
with that requirement.
By two weeks after the flood it appeared some acquisition projects might be possible.
Citizen acceptance was mixed, making political leadership especially tricky. By hinting at
floodplain acquisition possibilities, the city raised tremendous hopes among flood victims
who didn't want to rebuild. At the same time, this possibility triggered equally
tremendous anger among flood victims who wanted to rebuild and get on with their lives.
Two of the
five City Commission members opposed any acquisition program, contending that costs
exceeded benefits. Commissioners Walter Hall and Roy Gardner argued that the proposed
buy-out was really a "bail-out" for people who should have known they were
living in a flood zone.
One of the opponents publicly scored Mayor Young and Commissioner Metcalfe for raising
"false hopes" for flood victims.
"A false hope is better than none," countered flood victim Abbot Grant, whose
home was flooded to the ceiling. It was his sixth flood since 1970.
Eventually, after bitter debate, an acquisition project was approved.
1984 highlights
Here are some highlights of Tulsa's 1984 flood buy-out.
- Program scope. The Tulsa team's initial recommendation was for purchase of 535 flooded
homes in 20 areas. After debate, the program was scaled back to about 300 homes in nine
sites. Two years later, the city also bought the flooded Holiday Mobile Home Park with 228
floodprone pads, before it was rebuilt.
- Acquisition process. Mayor Young and Commissioner Metcalfe strongly believed that the
city should handle the acquisitions swiftly, with maximum possible care and consideration
for flood victims.
Young's administrative assistant, Twyla Mason Gray, led the
team that managed individual negotiations and acquisitions. The city and each seller
obtained appraisals, based on fair market value the day before the flood. The city
intended that all purchases be voluntary. At one point, some 15 owners threatened to sue
the city, but as the process proceeded they withdrew their objections. Ultimately, the
buy-out was completed without condemnations.
- Rebuilding moratoria. On June 1 ... Day 5 after the May 27 flood ... the city
established a moratorium on mobile home hookups for 30 days, until the city could conduct
case-by-case reviews. It was to be the first of a series of moratoria. The most important
was imposed on Day 15 (June 11), when the city designated high-hazard areas and denied
permits for all repairs until the city could complete its mitigation plan. An appeal
process was added on Day 18, allowing some flexibility for case-by-case reviews. After
initial confusion about standards, the city adopted a policy that building permits would
be required for any structure with more than 18 inches of flooding or repair costs
exceeding $5,000. This standard was recommended by FEMA and SBA, which established a
policy that SBA loans could be used toward relocation if a structure was in an area where
the city prohibited repair.
- Hotline, media, and outreach. Demands for information were overwhelming. Fortunately,
Tulsa's news media were sophisticated, having been through many floods, so news coverage
remained focused on recovery long after the flood. Of course, the coverage was not all
positive, and the media could not cover all the individual issues that victims faced. To
improve information flow, the city set up a hotline, staffed in part by mental health
volunteers. By Day 26 (June 22), the city also set up a mobile office. Later, periodic
mailings and newsletters were sent to interested citizens in the final acquisition areas.
One television station carried live coverage of Mayor Young's speech on Day 46 (July 11),
when he announced the details of the acquisition and mitigation program.
- Holiday Mobile Home Park. The most dangerous site during the flood was probably Holiday
Mobile Home Park, which had 228 floodprone units swamped by swift, high waters. On the
city's recommendation, the Federal Interagency Hazard Mitigation Team urged Tulsa to
refuse to reconnect utilities to any of the severely damaged homes. Specifically, the city
required certification by a registered professional engineer that each home could be
successfully tied down, even during a raging flood. Park owners sued the city. Eventually,
two years after the flood, the city agreed to settle by purchasing the park for $2
million. Because the expenditure was for a settlement judgment, the city was able to tap
the sinking fund for the money. The cleared park has been retained as floodplain open
space.
- Structural versus nonstructural issues. Opponents also argued that acquisition was not
fiscally sound and that the funds would be better used to build structural projects.
Proponents countered by arguing that nonstructural projects are still projects, as
necessary for the storage or conveyance of flood water as any concrete structures. The
acquisition program was "engineeringly sound and morally right," argued Street
Commissioner Metcalfe, just before the successful (though split) City Commission vote to
approve the mitigation program.
- Hardship Committee. Popular belief was that flood victims would oppose relocation, and
some initially did, for varying reasons, but ultimately,
Tulsa's 1984 buy-out
was conducted on a voluntary basis, with no need for condemnation. A far greater political
problem was limiting the buy-out to 306 single-family homes, when the flood had damaged
nearly 7,000 buildings. Survivors were traumatized and frightened. Many of the requests
for buy-outs were emotionally wrenching, from people in dire circumstances. To deal with
the problem, the city established a hardship committee to hear appeals. Ultimately, the
committee made minor adjustments, adding and deleting a few properties in the acquisition
plan, but the committee provided a needed relief valve during a time of community crisis.
- Priority criteria. Tulsa was incredibly lucky to be able to tap consultants, local team
members, and political leaders who had broad and deep knowledge of the city, its flood
issues and floodplains, and federal issues. Many decisions could therefore be based on
seasoned judgment, rather than detailed written criteria. The team's difficult decisions
on whether to include or exclude properties from buy-out areas were guided, in general, by
evaluating danger, flood depth and velocity, damage, and existing project plans. Because
funds were limited, only single-family homes ... and later, mobile home sites ... were
acquired.
- Spin-off benefits. Tulsa accrued many benefits from the 1984 post-flood acquisition
program. Given their histories, the cleared homes would undoubtedly have flooded again. In
some cases, owners moved their own homes to dry sites; the city purchased the properties
and sold them, at scrap value, back to owners. In some cases, the Tulsa redevelopment
agency moved flooded but sound homes to land previously cleared in a former slum ... where
the moved houses served to create a market that subsequently stabilized the neighborhood.
In several instances, cleared floodplains were used for flood control works. In other
cases, the cleared lands are used for open space and recreation, including hiking and
biking trails.
- Funding for single-family acquisitions. Tables 1 and 2 list costs and fund sources for
Tulsa's major acquisition programs, including the 1984 acquisition. Financing had to be
delicately balanced.
By chance, Tulsa had capital sales tax funds that were unallocated at the time of the
flood. Opponents were successful in preventing direct expenditure of sales tax funds. The
city instead sold revenue bonds, pledged the unallocated sales tax toward repayment, and
used the interest to finance the city's share of the flood buy-out. This maneuver was
necessary to avoid charges that the city had used the sales tax for a purpose not approved
by voters.
Politically, the buy-out was a stronger proposition if leaders could argue that they were
leveraging federal funds. They got an early ruling that flood insurance checks (for
structure damage, not contents) and SBA loans could be used toward the acquisition. After
negotiations between FEMA's disaster coordinator, Robert Broussard, and Mayor Young, FEMA
agreed to accept an application for 1362 funds. The process was complex, and the timing
was critical. FEMA assigned staff to work with the city to iron out all the issues.
FEMA divided the cost of acquisition on a 50-50 basis after deduction of flood insurance
claims. Table 1 shows cost sharing for the 1362 project area.
In addition to the use of Section 1362 funds and flood insurance claims, the 1984-85 phase
of the Tulsa program took advantage of the availability of federal temporary housing
assistance and Small Business Administration involuntary relocation loans.
By using these post-disaster assistance sources, the 1984 program's net cost to the city
was only 65 percent of the total cost, significantly lower than net costs in 1974 and 1979
acquisition programs, as shown in Table 2.
Table 2
TULSA FLOOD ACQUISITION COST, 1974-84
| Year |
1974-76 |
1979-82 |
1984-85 |
| Parcels |
33 |
30 |
284a |
| Purchase price |
$867,731 |
1,347,032 |
16,460,916 |
| Appraisals/legal |
$7,993 |
5,600 |
157,476 |
| Relocation/moving |
$4,981b |
394,993c |
647,156d |
| Administrative |
$22,560 |
33,459 |
364,634 |
| TOTAL COST |
$903,265 |
1,781,084 |
17,630,182 |
| LESS |
. |
. |
. |
| Sale of structure/salvage & rental |
$104,306 |
83,529 |
865,496 |
| Insurance claims |
... |
... |
3,375,411 |
| Section 1362 funds |
... |
... |
1,864,428 |
| CITY'S NET COST |
$798,959 |
1,697,555 |
11,524,847 |
| CITY % OFTOTAL COST |
88.5% |
95.3% |
65.4% |
| a) As of October 15, 1985 |
| b) Actual moving expenses |
| c) Uniform relocation assistance |
| d) Moving expense and reimbursements |
Post-flood Acquisition Priority
Criteria
With 7,000
buildings flooded in 1984 and limited funds, Tulsa leaders faced difficult decisions on
setting priorities for floodplain acquisition. Selection criteria included the following:
- Was the property needed for a flood project, per master plans?
- Was the structure a single-family home? Did people sleep there?
- Was the property within a FEMA or city floodway?
- Was flood depth greater than 4 feet above the first floor?
- Was velocity greater than 4-6 feet per second?
- Was depth times velocity greater than 6?
- Was there a concealed hazard, poor access or egress, isolation, or other site
consideration that created particular danger?
- Was it adjacent to an existing/proposed improvement or conveyance?
- Was the property needed for some other public use?
- Did the owner have flood insurance that could be applied toward relocation or 1362
eligibility?
- Had the house flooded repeatedly?
- Was the owner willing to sell?
- What was the effect on other properties, upstream or downstream?
- Was the property part of a contiguous-parcel acquisition area?
- Was it part of a coherent area reuse plan?
- Would it experience residual flooding, even when all planned flood control projects were
complete?
- What was the property cost, in relation to available funds?
- Was the area or property contaminated by toxics?
 
[Preface]
[Overview] [History] [Buyout or Bailout?] [Garden City & Beyond]
[Conclusion] [References] [Appendix]
|